Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.000 | 0.7 | 0.700 | 0.600 |
129W675 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.17
Resanction Cost :
32.17
Tentative Cost :
32.17
Exp. Upto Last Fy : 10.45
For CFY 2024-2025
Remaining : 21.72
Demand : 15.00
Allotment : 8.27
Exp in CFY : 8.27
Total Up to Date Exp : 18.72
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 86 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in progress -- as on 30-Jun-2024
Physical Peramenters