Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.52 | 0.52 | 0.520 | 0 | 0.000 | 0.000 |
129W676 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.73
Resanction Cost :
30.73
Tentative Cost :
30.73
Exp. Upto Last Fy : 17.78
For CFY 2024-2025
Remaining : 12.95
Demand : 10.00
Allotment : 2.31
Exp in CFY : 2.31
Total Up to Date Exp : 20.09
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व अवशेष -- as on 30-Apr-2024
Physical Peramenters