Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.65 | 0.65 | 0.500 | 0.15 | 0.150 | 0.000 |
129W680 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 60.64 Lacs
Resanction Cost : 60.64 Lacs
Exp. Upto Last Fy : 15.33 Lacs
For CFY 2024-2025
Remaining : 45.31 Lacs
Demand : 35.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 15.33 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
10 months 2 hours ago
19 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 30-Apr-2024
Physical Peramenters