Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.75 | 0.75 | 0.350 | 0.4 | 0.400 | 0.250 |
129W685 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.11
Resanction Cost :
54.11
Tentative Cost :
54.11
Exp. Upto Last Fy : 15.00
For CFY 2024-2025
Remaining : 39.11
Demand : 27.00
Allotment : 9.10
Exp in CFY : 9.10
Total Up to Date Exp : 24.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 80 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
1 week 3 days from now
28 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters