Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.700 | 0.6 | 0.600 | 0.000 |
129W686 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-46134, दिनांक 31.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 58.37 Lacs
Resanction Cost : 62.75 Lacs
Exp. Upto Last Fy : 32.55 Lacs
For CFY 2024-2025
Remaining : 30.20 Lacs
Demand : 0.17 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 32.55 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 week 5 days ago
06 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 08-Dec-2023
Physical Peramenters