Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.350 | 0.15 | 0.150 | 0.000 |
129W692 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-46134, दिनांक 31.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
38.82
Resanction Cost :
38.82
Tentative Cost :
38.82
Exp. Upto Last Fy : 12.00
For CFY 2024-2025
Remaining : 26.82
Demand : 18.00
Allotment : 10.00
Exp in CFY : 3.12
Total Up to Date Exp : 15.12
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 70 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वर्तमान में स्थानीय ग्रामीणों द्वारा विवाद किया जा रहा है। -- as on 01-Jul-2024
Physical Peramenters