Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.600 | 0.600 |
129W715 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-54552, दिनांक 22.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.68
Resanction Cost :
18.68
Tentative Cost :
18.68
Exp. Upto Last Fy : 12.52
For CFY 2024-2025
Remaining : 6.16
Demand : 6.16
Allotment : 5.00
Exp in CFY : 4.85
Total Up to Date Exp : 17.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
7 months 3 weeks ago
22 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 month 2 weeks ago
30 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024