Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.350 | 0.25 | 0.100 | 0.000 |
129W719 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-57969, दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 24.17 Lacs
Resanction Cost : 24.17 Lacs
Exp. Upto Last Fy : 17.16 Lacs
For CFY 2024-2025
Remaining : 7.01 Lacs
Demand : 7.01 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.16 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
6 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in progress -- as on 06-Mar-2024