Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.81 | 0.81 | 0.480 | 0.33 | 0.020 | 0.020 |
129W720 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-57969, दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.00
Resanction Cost :
24.00
Tentative Cost :
24.00
Exp. Upto Last Fy : 20.45
For CFY 2024-2025
Remaining : 3.55
Demand : 3.55
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 20.45
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 100 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 month 2 weeks ago
30 May 2024
Remark
Bottelneck: no issue
work completed -- as on 01-Jun-2024
Physical Peramenters