Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.6 | 0.6 | 0.000 | 0.6 | 0.600 | 0.200 |
129W723 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-49430, दिनांक 29.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.60
Resanction Cost :
21.60
Tentative Cost :
21.60
Exp. Upto Last Fy : 5.31
For CFY 2024-2025
Remaining : 16.29
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 35 %
Sanction on :
7 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ग्रामीणों के आपसी विवाद के कारण कार्य बाधित है। -- as on 01-Jun-2024
Physical Peramenters