Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-49430, दिनांक 29.11.2023
TS Amount (lakhs) : 68.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
68.44
Resanction Cost :
68.44
Tentative Cost :
55.00
Saving
13.44
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
68.44
Demand :
55.00
Allotment :
20.00
Exp in CFY :
54.23
Total Up to Date Exp :
54.23
Work completed
Sanction on : 11 months 3 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
100 %
Tentative Completion date on : 2 months 1 week ago
15 Sep 2024
Actual Completion Date : 5 months 3 weeks ago
31 May 2024
Physical Linear Components
Remark
Overall Saving 13.44 has been recorded as expected cost of work reduced from 68.44 to 55 . Due to Below Tender Rate. -- as on 01-Aug-2024
Assets :
Work not linked with IM