Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.1 | 1.1 | 0.000 | 1.1 | 1.100 | 0.500 |
129W728 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-49430, दिनांक 29.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.46
Resanction Cost :
50.46
Tentative Cost :
50.46
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 50.46
Demand : 35.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 50 %
Sanction on :
7 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
1 month 3 weeks from now
13 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 30-Apr-2024
Physical Peramenters