Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.000 | 0.8 | 0.800 | 0.000 |
129W733 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई-फाईल सं0-49430 , लोक निर्माण अनुभाग-2, दिनांक 29.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
37.88
Resanction Cost :
37.88
Tentative Cost :
37.88
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 37.88
Demand : 27.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
7 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
ग्रामीणों के मध्य आपसी विवाद होने के कारण कार्य बाधित। -- as on 02-May-2024
Physical Peramenters