Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.000 | 0.8 | 0.800 | 0.000 |
129W735 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई-फाईल सं0-49430 , लोक निर्माण अनुभाग-2, दिनांक 29.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 32.89 Lacs
Resanction Cost : 32.89 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 32.89 Lacs
Demand : 22.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 20 %
Sanction on :
5 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 30-Apr-2024
Physical Peramenters