Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 2 | 2 | 0 |
12W13 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 822 / ।।। -(2) /08-53 (एम0एल0ए0) / 07 दिनांक 24.03.2008
TS Amount (lakhs) : 105 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy : 101.60
For CFY 2024-2025
Remaining : 3.40
Demand : 3.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 101.60
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
पुनरीक्षित आगणन लम्बाई 3 किमी0, लागत रू0 189.00 लाख का मुख्य अभि0 हल्द्वानी के पत्रांक 2199/12 याता-हल्द्वानी/2022 दि0 23.5.2023 द्वारा सचिव लो0नि0वि0, देहरादून को पे्रषित। -- as on 21-Jun-2023
Physical Peramenters