Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 0.5 | 0.000 | 0.5 | 0.200 | 0.000 |
12W181 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5938/ ।।। (2) / 2012 - 25 (सा0) / 11 दिनांक 26.11.2012
TS Amount (lakhs) : 72.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
72.33
Resanction Cost :
72.33
Tentative Cost :
72.33
Exp. Upto Last Fy : 54.57
For CFY 2024-2025
Remaining : 17.76
Demand : 17.76
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 54.57
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 100 %
Sanction on :
11 years 7 months ago
26 Nov 2012
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 31-May-2024
Physical Peramenters