Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 0.5 | 0.000 | 0.5 | 0.200 | 0.000 |
12W181 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5938/ ।।। (2) / 2012 - 25 (सा0) / 11 दिनांक 26.11.2012
TS Amount (lakhs) : 72.33 Lacs
Financial Detail
Sanction Cost : 72.33 Lacs
Resanction Cost : 72.33 Lacs
Exp. Upto Last Fy : 54.57 Lacs
For CFY 2024-2025
Remaining : 17.76 Lacs
Demand : 17.76 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 54.57 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
11 years 5 months ago
26 Nov 2012
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मा0 उच्च न्यायालय से स्थगन आदेश निरस्त होने के पश्चात् अनुबन्ध गठित। कार्य प्रगति पर। 0.400 किमी0 कार्य पूर्ण। -- as on 02-Apr-2024
Physical Peramenters