Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Span of Bridges [m] | 70 | 70 | 70 | 0 |
12W302 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2200/ ।।। (2) /57 एम0एल0ए0 /2016 टी0ए0सी0 दिनांक 25.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.70
Resanction Cost :
3.70
Tentative Cost :
3.70
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 3.60
Demand : 3.60
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 80 %
Sanction on :
7 years 11 months ago
25 Jul 2016
Tentative Completion date:
2 years 10 months ago
31 Aug 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सेतु का स्थल चयन अनुमोदित। एम0ओ0यू0 गठित। भू-वैज्ञानिक आख्या प्राप्त। मृदा परीक्षण पूर्ण। टी0सी0एस0 द्वारा 60 मी0 स्पान हेतु पी0पी0आर0 कनसलटैन्ट द्वारा गठित की गयी है। परीक्षण किया जा रहा है। -- as on 09-Dec-2022