Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 9 | 0 |
12W304 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2200/ ।।। (2) /57 एम0एल0ए0 /2016 टी0ए0सी0 दिनांक 25.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 35.00 Lacs
Resanction Cost : 35.00 Lacs
Exp. Upto Last Fy : 1.71 Lacs
For CFY 2024-2025
Remaining : 33.29 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
7 years 9 months ago
25 Jul 2016
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
वन भूमि प्रस्ताव में प्रतिहस्ताक्षर हेतु इस कार्यालय के पत्रांक 440/ 8 सी0 दि0 29.02.2024 को जिलाधिकारी को प्रेषित। -- as on 16-May-2024
Physical Peramenters