Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 9 | 0 |
12W304 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2200/ ।।। (2) /57 एम0एल0ए0 /2016 टी0ए0सी0 दिनांक 25.07.2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.00
Resanction Cost :
35.00
Tentative Cost :
35.00
Exp. Upto Last Fy : 1.71
For CFY 2024-2025
Remaining : 33.29
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.71
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
7 years 11 months ago
25 Jul 2016
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
दि0 29.05.24 को जिलाधिकारी नैनीताल से प्रतिहस्ताक्षर कराकर दि0 30.05.24 को प्रभागीय वनाधिकारी नैनीताल को प्रतिहस्ताक्षर हेतु प्रेषित। -- as on 04-Jun-2024