Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
12W360 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2231(अ)/।।।(2)/17-57 (एम0एल0ए0)/2017 दिनांक 14.09.2017
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 11.50 Lacs
Resanction Cost : 11.50 Lacs
Exp. Upto Last Fy : 1.90 Lacs
For CFY 2024-2025
Remaining : 9.60 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.90 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
6 years 8 months ago
14 Sep 2017
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
दि0 16/12/2023 को आॅनलाइन वी0सी0 में दिये गये निर्देशों के क्रम में मक डिस्पोजल हेतु नाप भूमि का चयन का लिया गया है। आपत्तियों के निराकरण हेतु वन अभ्यारण्य से दुरी का प्रमाण पत्र प्राप्त करने हेतु दि0 29/02/2024 तथा दि0 22/04/2024 को प्रभागीय वनाधिकारी देहरादून को पत्र लिखा गया है। माह मार्च में इस हेतु निर्धारित शुल्क भी जमा कर दिया है। प्रमाण पत्र अपेक्षित है। -- as on 30-Apr-2024
Physical Peramenters