Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 5.75 | 5.75 | 0 |
12W399 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेष सं0 5030/।।। (2)/18-57 (एम0एल0ए0)/2017 टी0सी0 - 1 दिनांक 11.10.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
40.40
Resanction Cost :
40.40
Tentative Cost :
40.40
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 40.30
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 1 %
Sanction on :
5 years 9 months ago
11 Oct 2018
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
दिनांक 29.05.24 से प्रभागीय वनाधिकारी नैनीताल के स्तर पर विचाराधीन। -- as on 04-Jun-2024
Physical Peramenters