Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 30 | 30 | 30 | 0 |
12W428 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 3414/।।। (2)/19-57 (एम0एल0ए0)/2017 टी0स्ी01 दिनांक 13.09.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
3.00
Resanction Cost :
3.00
Tentative Cost :
3.00
Exp. Upto Last Fy : 1.57
For CFY 2024-2025
Remaining : 1.43
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.57
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 10 months ago
13 Sep 2019
Tentative Completion date:
2 years 6 months ago
31 Dec 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य की डी0पी0आर0 मुख्य अभियन्ता के पत्रांक 962/12 याता हल्द्वानी/2022 दि0 13.03.2024 द्वारा रू0 121.39 लाख की स्वीकृति हेतु शासन को प्रेषित। -- as on 02-Apr-2024
Physical Peramenters