Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 |
12W441 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 367(1)/XXXVI(2)-09(बजट)/2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 202.46 Lacs
Resanction Cost : 202.46 Lacs
Exp. Upto Last Fy : 114.91 Lacs
For CFY 2024-2025
Remaining : 87.55 Lacs
Demand : 40.02 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 114.91 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
14 Jun 2021
Tentative Completion date:
2 months 1 week ago
09 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
work Complete. -- as on 08-Apr-2024
Physical Peramenters