Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 |
12W442 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 442(1)/XXXVI(2)/2021-41-दो(8)/17
TS Amount (lakhs) : 404.29 Lacs
Financial Detail
Sanction Cost : 461.15 Lacs
Resanction Cost : 461.15 Lacs
Exp. Upto Last Fy : 210.69 Lacs
For CFY 2024-2025
Remaining : 250.46 Lacs
Demand : 250.46 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 210.69 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 62 %
Sanction on :
2 years 11 months ago
14 Jun 2021
Tentative Completion date:
7 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
तृतीय / अन्तिम तल में कालम का कार्य प्रगति पर। प्रथम तल एवं द्वितीय तल में ईट चिनाई का कार्य प्रगति पर। -- as on 08-May-2024
Physical Peramenters