Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 10 | 0 |
12W446 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5682(1)/।।।(2)/21-57(एम0एल0ए0)/2017 टी0सी0आई दिं0 22.11.2021
TS Amount (lakhs) : 312.54 Lacs
Financial Detail
Sanction Cost : 312.54 Lacs
Resanction Cost : 312.54 Lacs
Exp. Upto Last Fy : 252.47 Lacs
For CFY 2024-2025
Remaining : 60.07 Lacs
Demand : 20.00 Lacs
Allotment : 8.39 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 252.47 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 98 %
Up to Date : 98 %
Sanction on :
2 years 5 months ago
22 Nov 2021
Tentative Completion date:
4 months 4 weeks from now
17 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारो, पैरापिट, काजवे, नाली आदि का निर्माण कार्य प्रगति पर। उक्त कार्य में रू0 59.45 लाख मात्र का व्यय राज्य योजना के अन्तर्गत किया गया है। -- as on 07-Mar-2024
Physical Peramenters