Work Profile Report [12W446]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 5682(1)/।।।(2)/21-57(एम0एल0ए0)/2017 टी0सी0आई दिं0 22.11.2021
TS Amount (lakhs) : 312.54 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
312.54
Resanction Cost :
312.54
Tentative Cost :
312.54
Exp. Upto Last Fy :
300.85
For CFY 2025-2026
Remaining :
11.69
Demand :
2.49
Allotment :
5.00
Exp in CFY :
0.00
Total Up to Date Exp :
300.85
In Maintenance After Completion
Sanction on : 4 years 3 weeks ago
22 Nov 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months from now
25 Apr 2027
Actual Completion Date : 1 year 8 months ago
25 Mar 2024
Physical Linear Components
Remark
Overall Saving 7 has been recorded as expected cost of work reduced from 312.54 to 305.54 . -- as on 15-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: