Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
12W447 :
Administrative Approval Detail : शा0 सं0 6014 (1)/।।। (2) /21-57 (एम0एल0ए0) 2017 टी0सी0आई0 दिनांक 11.12.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
106.25
Resanction Cost :
106.25
Tentative Cost :
106.25
Exp. Upto Last Fy : 44.02
For CFY 2024-2025
Remaining : 62.23
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 44.02
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 7 months ago
11 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 02-Apr-2024
Physical Peramenters