Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 45 | 45 | 45 | 0 |
12W451 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 22014 लोक निर्माण अनुभाग-2 देहरादून दिनांक 12.09.2022
TS Amount (lakhs) : 177.99 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
177.99
Resanction Cost :
177.99
Tentative Cost :
177.99
Exp. Upto Last Fy : 105.79
For CFY 2024-2025
Remaining : 72.20
Demand : 72.20
Allotment : 60.01
Exp in CFY : 0.00
Total Up to Date Exp : 105.79
Work completed
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 100 %
Sanction on :
1 year 10 months ago
12 Sep 2022
Tentative Completion date:
4 weeks 18 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष।
रू0 17.80 लाख राज्य योजना से व्यय किया गया हे।
-- as on 03-Jul-2024
Physical Peramenters