Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 18 | 18 | 18 | 0 |
12W467 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 47049 लोक निर्माण अनुभाग-2 देहरादून दिनांक 16.02.2023
TS Amount (lakhs) : 4.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
5.58
Resanction Cost :
5.58
Tentative Cost :
5.58
Exp. Upto Last Fy : 1.47
For CFY 2024-2025
Remaining : 4.11
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.47
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 35 %
Sanction on :
1 year 5 months ago
16 Feb 2023
Tentative Completion date:
4 weeks 19 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Site selection is complete. Formation of DPR is in progress. -- as on 03-Jul-2024
Physical Peramenters