Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.133 | 1.133 | 0.300 | 0.833 | 0.230 | 0.000 |
12W486 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 48226 लोक निर्माण अनुभाग-2 देहरादून दिनांक 17.05.2023
TS Amount (lakhs) : 60.67 Lacs
Financial Detail
Sanction Cost : 60.67 Lacs
Resanction Cost : 60.67 Lacs
Exp. Upto Last Fy : 35.83 Lacs
For CFY 2024-2025
Remaining : 24.84 Lacs
Demand : 20.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 35.83 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
1 year 2 days ago
17 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Oct-2023
Physical Peramenters