Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 1.800 | 0.2 | 0.000 | 0.200 |
12W487 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 47049 लोक निर्माण अनुभाग-2 देहरादून दिनांक 11.05.2023
TS Amount (lakhs) : 68.63 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
68.63
Resanction Cost :
68.63
Tentative Cost :
68.63
Exp. Upto Last Fy : 37.26
For CFY 2024-2025
Remaining : 31.37
Demand : 20.00
Allotment : 15.00
Exp in CFY : 8.00
Total Up to Date Exp : 45.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
11 May 2023
Tentative Completion date:
2 months 4 hours ago
17 May 2024
Actual Completion Date:
2 months 4 hours ago
17 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024
Physical Peramenters