Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 0.000 | 4.5 | 3.400 | 0.000 |
12W488 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन के ई फॅाईल संख्या-48226 दिनांक 14.07.2023 द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 248.64 Lacs
Financial Detail
Sanction Cost : 248.64 Lacs
Resanction Cost : 248.64 Lacs
Exp. Upto Last Fy : 77.10 Lacs
For CFY 2024-2025
Remaining : 171.54 Lacs
Demand : 150.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 77.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
10 months 5 days ago
14 Jul 2023
Tentative Completion date:
6 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.40 किमी0 में जी0एस0बी0 व जी02 का कार्य पूर्ण। 7 न0 कलर्वट का कार्य पूर्ण। -- as on 07-Mar-2024
Physical Peramenters