Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
12W495 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : संयुक्त सचिव के पत्रांक सं0 124607/01 (05)/2023 देहरादून दिनांक 25.05.2023
TS Amount (lakhs) : 85.55 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.55
Resanction Cost :
85.55
Tentative Cost :
85.55
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 85.55
Demand : 85.55
Allotment : 34.22
Exp in CFY : 23.22
Total Up to Date Exp : 23.22
Construction Started
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 2 %
Sanction on :
1 year 1 month ago
25 May 2023
Tentative Completion date:
2 months 3 weeks from now
11 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 24-Jan-2024
Physical Peramenters