Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11 | 11 | 0.000 | 11 | 11.000 | 11.000 |
12W498 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन के ई फॅाईल संख्या-48456 दिनांक 21.08.2023 द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 176.04 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
176.04
Resanction Cost :
176.04
Tentative Cost :
176.04
Exp. Upto Last Fy : 105.83
For CFY 2024-2025
Remaining : 70.21
Demand : 70.21
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 105.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
10 months 3 weeks ago
21 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 month 3 weeks ago
25 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण, दायित्व शेष। -- as on 07-Jun-2024