Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 2.2 | 0 |
12W505 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 48456 लोक निर्माण अनुभाग-2 देहरादून दिनांक 14.09.2023
TS Amount (lakhs) : 101.7 Lacs
Financial Detail
Sanction Cost : 101.70 Lacs
Resanction Cost : 101.70 Lacs
Exp. Upto Last Fy : 15.58 Lacs
For CFY 2024-2025
Remaining : 86.12 Lacs
Demand : 86.12 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 15.58 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 months 5 days ago
14 Sep 2023
Tentative Completion date:
3 months 2 weeks from now
07 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ। -- as on 14-Dec-2023
Physical Peramenters