Work Profile Report [12W506]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No-38519 Date-31.03.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
312.13
Resanction Cost :
312.13
Tentative Cost :
312.13
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
312.13
Demand :
240.00
Allotment :
180.00
Exp in CFY :
167.90
Total Up to Date Exp :
167.90
Construction Started
Sanction on : 1 year 7 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
43 %
Tentative Completion date on : 2 days 7 hours from now
26 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मार्ग के किनारे इण्टर लांकिग टाइल्स द्वारा पटरी का कार्य प्रगति पर। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand