Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 4.000 | 0.000 |
12W506 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No-38519 Date-31.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
312.13
Resanction Cost :
312.13
Tentative Cost :
312.13
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 312.13
Demand : 200.00
Allotment : 0.00
Exp in CFY : 72.02
Total Up to Date Exp : 72.02
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 30 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
SDBC in 3.4 km is complete and SDBC in 800 m is left. Interlocking tile in 600 m is complete. KC drain construction work is in progress. -- as on 12-Jul-2024