Work Profile Report [12W533]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई फॅाईल संख्या-53594 दिनांक 13.12.2023 द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1162.33
Resanction Cost :
1162.33
Tentative Cost :
1162.33
Exp. Upto Last Fy :
847.90
For CFY 2025-2026
Remaining :
314.43
Demand :
314.43
Allotment :
272.78
Exp in CFY :
213.91
Total Up to Date Exp :
1,061.81
Construction Started
Sanction on : 2 years 12 hours ago
13 Dec 2023
Physical Progress:
At start of FY 2025-2026 :
35 %
Up to Date :
90 %
Tentative Completion date on : 2 weeks 3 days from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
डामरीकरण का कार्य पूर्ण। रोड फर्नीचर का कार्य प्रगति पर। -- as on 23-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2025 PWD Uttarakhand