Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 30 | 30 | 0.000 | 30 | 0.000 | 0.000 |
12W537 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 22351 लोक निर्माण अनुभाग-2 देहरादून दिनांक 15.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
546.75
Resanction Cost :
546.75
Tentative Cost :
546.75
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 546.65
Demand : 200.00
Allotment : 60.00
Exp in CFY : 5.15
Total Up to Date Exp : 5.25
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
6 months 2 days ago
15 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Excavation for foundation of LHS side ht. 12 m is complete and at RHS side out of 22 m 21.50 m is complete . 0.5 m ht.excavation at RHS side is in progress. -- as on 12-Jul-2024
Physical Peramenters