Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 0.000 | 12 | 12.000 | 0.000 |
12W538 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के संख्या-272/ं।।।(2)/2024-01(प्रा0आ0)/2023 दिनांक 31.01.2024 द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 238.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
238.76
Resanction Cost :
238.76
Tentative Cost :
238.76
Exp. Upto Last Fy : 39.93
For CFY 2024-2025
Remaining : 198.83
Demand : 198.83
Allotment : 200.00
Exp in CFY : 74.90
Total Up to Date Exp : 114.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
3 weeks 4 days ago
22 Jun 2024
Actual Completion Date:
3 weeks 4 days ago
22 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 24-Jun-2024
Physical Peramenters