Work Profile Report [12W542]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन लोक निर्माण अनुभाग-2 के ई फॅाईल संख्या-62316 दिनांक 09.02.2024 द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
453.44
Resanction Cost :
453.44
Tentative Cost :
453.44
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
453.34
Demand :
380.00
Allotment :
102.86
Exp in CFY :
30.37
Total Up to Date Exp :
30.47
Construction Started
Sanction on : 9 months 2 weeks ago
09 Feb 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
18 %
Tentative Completion date on : 6 months 2 weeks from now
09 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्यस्थल पर जी0एस0बी0 एवं दीवार निर्माण का कार्य प्रगति पर। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand