Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
12W543 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं0 47302 लोक निर्माण अनुभाग-2 देहरादून दिनांक 27.02.2024
TS Amount (lakhs) : 53.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
53.89
Resanction Cost :
53.89
Tentative Cost :
53.89
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 53.89
Demand : 50.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
4 months 2 weeks ago
27 Feb 2024
Tentative Completion date:
4 weeks 18 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 08-Apr-2024
Physical Peramenters