Work Profile Report [130W11]

strengthening work from km 232.00 to km 274.00 on NH 119(534) under NH(O) 2020-21 in the state of Uttarakhand
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : NH-119/NEW-534/AP/UK/2021

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

299.31

Resanction Cost :

29931.43

Tentative Cost :

29931.43

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

29,931.43

Demand :

3,000.00

Allotment :

976.79

Exp in CFY :

976.79

Total Up to Date Exp :

976.79

Unstarted Work

Sanction on : 3 years 8 months ago

10 Feb 2022

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 1 month 3 weeks from now

31 Dec 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
42
42.47
0.000
42.47
0.000
0.000
Jobs
1
0
0
0
0

Remark

view all

Overall Excess requirement 29632.12 has been counted as tentative cost increased from 299.31 to 29931.43 . -- as on 15-Oct-2025

Rating : 4

No Forest Case in The Work

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: