Work Profile Report [130W2]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : job no. 119 (534)-UR-2020-2021-574)
TS Amount (lakhs) : 8232.03 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
8232.03
Resanction Cost :
8232.03
Tentative Cost :
8232.03
Exp. Upto Last Fy :
243.94
For CFY 2024-2025
Remaining :
7,988.09
Demand :
3.34
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
243.94
Work completed
Sanction on : 3 years 5 months ago
17 Jun 2021
Physical Progress:
At start of FY 2024-2025 :
95 %
Up to Date :
100 %
Tentative Completion date on : 6 months 3 weeks ago
30 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
WORK IS COMPLETED
26.00 Km DBM completed
26.00 km BC work completed
45 no culvert is completed
30.97 km drain is completed
9.5 km protection work is completed
crash barrier is completed
-- as on 06-Oct-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3 Road 4
Bridges on The Basis of AI: rcc bridge TALGAD BRIDGE Pedestrain Bridge at Deghat Bounsal Bailly bridge Jamtari Baily Bridge Satpuli bridge arch bridge RCC bridge RCC bridge arch bridge RCC bridge