Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 32 | 32 | 32 | 0 | ||
No of Bridges | 3 | 3 | 3 | 0 | ||
Span of Bridges [m] | 50 | 50 | 50 | 0 | ||
Jobs | 9 | 9 | 9 | 0 |
130W2 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3 Road 4
Bridges on The Basis of AI: rcc bridge TALGAD BRIDGE Pedestrain Bridge at Deghat Bounsal Bailly bridge Jamtari Baily Bridge Satpuli bridge arch bridge RCC bridge RCC bridge arch bridge RCC bridge
Administrative Approval Detail : job no. 119 (534)-UR-2020-2021-574)
TS Amount (lakhs) : 8232.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
8232.03
Resanction Cost :
8232.03
Tentative Cost :
8232.03
Exp. Upto Last Fy : 243.94
For CFY 2024-2025
Remaining : 7,988.09
Demand : 3.34
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 243.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 99 %
Sanction on :
3 years 1 month ago
17 Jun 2021
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
98.76% WORK IS COMPLETED
25.700 Km DBM completed
25.700 km BC work completed
45 no culvert is completed
30.97 km drain is completed
9.5 km protection work is completed
crash barrier is completed
-- as on 04-May-2024
Physical Peramenters