Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.13 | 8.13 | 1.400 | 6.73 | 6.730 | 6.530 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
131W11 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/Annual Plan/ 2021-22/Rudraprayag/02 (Comp. No.212162)
TS Amount (lakhs) : 9913.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
9913.41
Resanction Cost :
9913.41
Tentative Cost :
9913.41
Exp. Upto Last Fy : 1,325.32
For CFY 2024-2025
Remaining : 8,588.09
Demand : 6,260.00
Allotment : 0.00
Exp in CFY : 2,607.59
Total Up to Date Exp : 3,932.91
Construction Started
Physical Progress:
At start of FY 2024-2025 : 27 %
Up to Date : 57 %
Sanction on :
1 year 10 months ago
12 Sep 2022
Tentative Completion date:
8 months 4 days from now
22 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 00: Not Started
Bottelneck: no issue
DBM & DLC work in progress. -- as on 28-Mar-2024
Physical Peramenters