Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.91 | 1.91 | 0.000 | 1.91 | 1.910 | 1.910 |
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
131W12 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UKlAnnual Plan/2022-23Rudraprayag/03 (Comp.213411)
TS Amount (lakhs) : 4743.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4743.37
Resanction Cost :
4743.37
Tentative Cost :
4743.37
Exp. Upto Last Fy : 1,315.41
For CFY 2024-2025
Remaining : 3,427.96
Demand : 1,526.00
Allotment : 0.00
Exp in CFY : 1,165.06
Total Up to Date Exp : 2,480.47
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 95 %
Sanction on :
1 year 9 months ago
10 Oct 2022
Tentative Completion date:
1 month 3 weeks ago
23 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 00: Not Started
Bottelneck: no issue
Sliding & Sinking zone treatment in progress -- as on 28-Mar-2024
Physical Peramenters