Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
131W16 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/AP/ 2022-23/Tunnel Revised Estimate (Comp. No.215054)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
543.93
Resanction Cost :
543.93
Tentative Cost :
543.93
Exp. Upto Last Fy : 46.43
For CFY 2024-2025
Remaining : 497.50
Demand : 472.00
Allotment : 0.00
Exp in CFY : 67.52
Total Up to Date Exp : 113.95
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 25 %
Sanction on :
1 year 4 months ago
24 Feb 2023
Tentative Completion date:
4 months 3 days from now
21 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
work in progress. -- as on 17-Feb-2024
Physical Peramenters