Work Profile Report [131W17]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/Annual Plan/ 2021-22/Rudraprayag/11 (Comp. No.217886)
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4241.25
Resanction Cost :
4241.25
Tentative Cost :
4241.25
Exp. Upto Last Fy :
734.73
For CFY 2024-2025
Remaining :
3,506.52
Demand :
2,523.00
Allotment :
0.00
Exp in CFY :
1,412.42
Total Up to Date Exp :
2,147.15
Construction Started
Sanction on : 1 year 9 months ago
08 Feb 2023
Physical Progress:
At start of FY 2024-2025 :
27 %
Up to Date :
70 %
Tentative Completion date on : 3 months 3 weeks from now
18 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress. -- as on 29-Sep-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand