Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
131W18 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/AnnualPlan/2022-23/Rudraprayag/14 (Computer No. 219923)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2600.30
Resanction Cost :
2600.30
Tentative Cost :
2600.30
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 2,600.30
Demand : 1,474.00
Allotment : 0.00
Exp in CFY : 415.22
Total Up to Date Exp : 415.22
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 37 %
Sanction on :
1 year 4 months ago
09 Mar 2023
Tentative Completion date:
6 months 2 weeks from now
02 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work started on 03.02.2024 -- as on 28-Mar-2024
Physical Peramenters