Work Profile Report [131W18]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/AnnualPlan/2022-23/Rudraprayag/14 (Computer No. 219923)
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2600.30
Resanction Cost :
2600.30
Tentative Cost :
2600.30
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
2,600.30
Demand :
1,474.00
Allotment :
0.00
Exp in CFY :
415.22
Total Up to Date Exp :
415.22
Construction Started
Sanction on : 1 year 8 months ago
09 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
37 %
Tentative Completion date on : 2 months 1 week from now
02 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work started on 03.02.2024 -- as on 28-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand