131W19 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Rudraprayag/10 (Computer No. 215145)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
7507.12
Resanction Cost :
7507.12
Tentative Cost :
7507.12
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 7,507.12
Demand : 2,500.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
1 year 7 months from now
04 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work started on 05.03.2024 -- as on 28-Mar-2024