Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.9003 | 0.9003 | 0.500 | 0.4003 | 0.680 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 200 | 200 | 0.000 | 200 | 200.000 | 0.000 |
131W5 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : F. No. RO/UK/12014/78/2018-19/Annual Plan (Part-II)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24852.00
Resanction Cost :
24852.00
Tentative Cost :
24852.00
Exp. Upto Last Fy : 12,028.78
For CFY 2024-2025
Remaining : 12,823.22
Demand : 5,000.00
Allotment : 0.00
Exp in CFY : 743.81
Total Up to Date Exp : 12,772.59
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 86 %
Sanction on :
3 years 5 months ago
15 Feb 2021
Tentative Completion date:
11 months 3 weeks from now
12 Jul 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 07: Nodal
Bottelneck: no issue
Work in progress. -- as on 13-Mar-2023