Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 18.7 | 18.7 | 0.000 | 18.7 | 1.400 | 0.000 |
131W7 :
Road ID on IM : Road 1
Bridges on The Basis of AI:
Administrative Approval Detail : एन0एच0/12014/49/2015-यू0आर0/एन0एच0-।।
TS Amount (lakhs) : 14147 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14147.00
Resanction Cost :
14147.00
Tentative Cost :
14147.00
Exp. Upto Last Fy : 8,734.90
For CFY 2024-2025
Remaining : 5,412.10
Demand : 2,435.00
Allotment : 0.00
Exp in CFY : 141.62
Total Up to Date Exp : 8,876.53
Construction Started
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
8 years 6 months ago
08 Jan 2016
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: Other Reason
Land acquisition issue at silli & Tilwara village. -- as on 27-Jul-2021
Physical Peramenters