Work Profile Report [132W14]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/RoadSafety/2023-24/Doiwala/01 Dt 06.03.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
884.81
Resanction Cost :
884.81
Tentative Cost :
884.81
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
884.81
Demand :
0.55
Allotment :
561.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
none
Sanction on : 1 year 7 months ago
06 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
32 %
Up to Date :
95 %
Tentative Completion date on : 3 days 5 hours ago
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work is in progress. -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: